Hi All,
I am trying to assign material on activities thru BOM-PS transfer (CN33) and also want to do assembly thru network ( as i do not want go thru production process in PP), I have created a BOM for item A (main item) , where item B,C and D are its sub component . I have created four activities in projects and defined reference point in each activity and BOM components. Now i opened transaction CN33 , i clicked on "transfer button" ( 3rd for the left at the top) here i entered project definition , header material (i.e A) and reference point . Now i am running CN33 , system is succesfuly assigning component B,C and D to the activities but item A is not getting assigned on the activity , but as fas as i know logically header material i.e A should have also got assigned on the activity with negative quantity.
Please suggest why header material is not getting assigned on the activity.
Thanks
Dear Akhil,
BOM transfer only assign component of BOM not header material with -ve quantity.
you have to assign this manually with -ve quantity. so this will get generated (Auto GR in project stock while confirmation and goods movement via 581 Q ).
thanks
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Akhil,
In transfer section, are you entering plant also?
Regards
Shrikant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
IN 'transfer control', also mention the WBS element alongwith Project definition.
Then you try again.
Regards,
Mahendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.