The requirement is that using third party process, in order to monitor the transportation, need to create the inbound delivery, but the question is that I test the inbound delivery goods receipt at the client plant and storage location not the customer location, so how to realize the inbound delivery for goods receipt at the customer location?
Regards
Tony
Hi Tony,
Your query is not very clear. Could you please elaborate more in detail about your requirement
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kumar,
The client is using third party process-Item category-TAS, they want to get the transportation information about the vendor ships the goods to the customer. Now, we are discussing the requirement.
I try to test it through inbound delivery from PO, then shipment document.
But when I create the shipment document, determinate the leg, the source is the vendor address, the destination is the client plant not the customer address.
Regards
Tony
Hi Tony,
The system defaults the plant address as the destination in P.O in the delivery address tab, but you can change this address to required customer address. For that you need to first define the customer address using MEAN transaction and then enter the address number (created in MEAN) in the delivery address tab in address field for each P.O item.
Regards
Vijay
Hi Tony,
What i understood from the above statment is that you have a customer(Cust1) and vendor (Vend1) & your plant location (Plant1). Normally Vend1 supplies the material to Plant1 and from Plant1 you distribute the goods to the Cust1)
In the above scenario you want to dispatch material directly from the Vend1 to the Cust1 and same time you want the stock should reflect in "In-Transit" in your system
If my understandin is correct then the correct flow of document should be
1) Vendor will send you a ASN which should create a Inbound delivery in your system which will have supplying plant as Vend1 and Receiving plant as Plant1
2) you should receive the goods in your system
3) Create a outbound delivery , Shipment from your system and dispatch the goods to the customer. This will have supplying plant as your Plant1 and Receiving location as Cust1
The above process will ensure that you are taking the ownership of the material before transfering the goods to the customer however this process is having some pros and cons e.g. what if the there is a transit loss / transit damage once goods reach at customer (Cust1)
Please let me know if the above steps make sense