I searched in SAP forum but i dint get the solution for my query.
I want to create only PR by adding material component in project with item cat L (stock) with out reservation creation.while am trying to add material component the for stock item the system automaticly generats the reservation and PR number.
But my requirement is to generate automatic only PR not reservation for stock (Item Cat L)
Pls share your valuable solution.Thanks in Advance.
Please check in SPRO> procurement indicators for material components (OPS8).
maintain item category L with Preq network.
Please check if it works and revert.
Regards
Ankur
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thank u for replay.
I did but it is generating reservation with PR .I tried with various settings by doing in procurement indicator OPS8.But cant achieved.
But with selecting planned independent requirment for WBS and pelim req for WBS in procurement option with L, with this i can create PR with out reservation for stock item.But the cost planning is not tacking place.So i checked in OPSV (Appended plan update) for order type 20.here the tick mark is there.But i dont know why it is not updating plann cost for these two options.
Ankur: I runned CJEN and CJBN still the cost paln is not updating.
Amaresh: Control Key Config, the cost check bok is selected for all control key.
sanjeev: for othe procurement indicator thet reservation with PR creation the cost is updating.So i think the N/W costing config is working fine.
Any procurement indicator config have to do in(OPS8).So that the PR with out Reservation will generate.
thank To all.