Plan & actual schedule graphs in planning board....

karthik_k3
Explorer
0 Kudos

Hi experts,


Is there any possibility to see both plan & actual graphs of the schedule in CJ20N planning board?


Generally it shows plan schedule in red color. I want to see other line with separate color for actual confirmation schedule. Ofcourse i am able to see the separate graph line when i confirm the activity completely. But i need to see the graph line for partial confirmation too...


Is it possible in SAP?

And also when i am trying to see the capacity overview graph in planning board by checking required WBS, it says There are no capacity requirements for the current selection and settings. I want to see the bar chat on the screen. I tried many ways,but couldn't find out.


Can you show some light for the above 2 issues?

Thanks & Regards.

Karthik

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Unfortunately this function is not availble in project systems Gantt chart.

However you can have dates displaying plan and actual dates for the activities.

On your second issue, please check if all customization in place required for capacity planning.

It seems there are no requirements which are using available capacity so you are getting this message.

Regards,

Mahendra