SNP Best practices on House keeping sequence.

Former Member
0 Kudos

Hi Experts.,

Need advise and best practice on how to schedule the jobs in sequence for Managing SNP data.

Currently we do the following. in sequence on a weekly basis.

1) Planning area initialization

2) OM17

3) adjust timeseries object - /SAPAPO/TS_LCM_PLOB_DELTA_SYNC

4) Consistency check for existing time series network - /SAPAPO/TS_LCM_CONS_CHECK

5) / SAPAPO/TS_LCM_REORG_SNP – Master Data consistency check for Livecache timeseries in SNP. – monthly.

6) /SAPAPO/TS_LCM_REORG – check livecache time series master data. – monthly.

are there any other or change the sequence?

hope this would delete all the Queue entries at data base level.

Regards

Rorie

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Rorie,

I am not aware of any 'Best Practices' published by SAP for 'SNP Housekeeping'. 

Recommended regularly scheduled processes are mentioned in the Operations Guide.

http://service.sap.com/~sapidb/011000358700001187132011E

Also, check out

http://service.sap.com/~sapidb/011000358700004718192003E

for SNP stuff.