on 01-09-2013 8:43 AM
hi
once spare is procured through a wbs and brought to stock and budget get reduced form the wbs .
again while issuing the spare to maint. order again the budget check will happen to the wbsor how is it happen?
hello,
When you transfer from stock to WBS the budget is consumed from the WBS. When you issued the stock the budget is available again.
regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
in my case wbs released value and assigned value are same means no budget avalable when t reservation happens to issue spare and it credit the wbs and debit the maint. order it gives error budget not avalable.
i could not understand this as it should increase the budget avalable in wbs since its credit.
pls calrify me