Does Budget check happen Budget check at Reservation & Goods issue?

in standard PS

Message was edited by: Moderator - Basic question, Spend time in reading SAP Help files and searching the forum.

Accepted Solutions (0)

Answers (1)

Answers (1)

sanjeevc
Active Contributor
0 Kudos

Yes, If Budget check availablity is active then system check both business entries as Reservation & Goods issue as well and availability check group should be ++ in tolerance group colomn. you can check this in system status as AVAC for project object.

Regards,

Sanjeev

former_member604117
Participant
0 Kudos

i have tested  it does not in GI but maintenace order during resrvation it is checking?