Error termination - RECN

Former Member
0 Kudos

experts,

need your help, I have a contract commencing on 01.05.2012 and is a condition that validates (01/05/2012 until 07/31/2012).

When I try to terminate this contract it generates error on cash flow.

The contract would have to terminate?

The favor will go FI?

Thank you.

Accepted Solutions (0)

Answers (1)

Answers (1)

franz_posch
Active Contributor
0 Kudos

Hi,

please provide more details about the error termination.

Which error message occurs? (message id and number, message text)

Which actions were performed and at wich stage exactly the error is raised?

Thanks.

Regards, Franz

Former Member
0 Kudos

Thanks for the help.

Here more information about the error.

Former Member
0 Kudos

The contract should not calculate the amount until 03/07 and return the rest at the time of termination?

franz_posch
Active Contributor
0 Kudos

Hi,

reason for the error might be that the customizing for reference flow types for follow-up postings is missing.

I assume that the error does not occur if the period 07 is not posted yet.

Regards, Franz

Former Member
0 Kudos

Hello alright!

Thanks for the assistance here and in NOTES (SAP). rs.rs..

So if the contract is not released in RERAPP I can terminate.

But with the contract launched in RERAPP the system generates error on cash flow.

What is the process recommended to the SAP?

It would throw all conditions, terminate the contract and then lnaçar?