on 12-31-2012 9:18 AM
Hi,
We have created one Z tcode through which project structure get created with WBS & activties.
Activies are created with status as "CRTD"
However sometimes we get 1-2 activites which doesn't have any system status...its showing Blank
Due to blank status I unable to release that Network / WBS .
Anyone faced similer type of error / know about such behaviour pls help.
Regards
Tejpal.
It seems there is an inconsistency with the system status. Please run program CNSTATUS (in SE38) followed by CJEN.
Also, check with your ABAPer, may be there is some inconsistency in your program.
Regards
Ankur