on 12-26-2012 7:40 AM
Dear All,
How we can use Collective PR Indicator in SAP PS ??
I want to make one purchase order for the Project.
Thanks.
Hi,
Apart from above this function would work if you check mark collective functionlity in network type parameter in t-code OPUV.
If you do not set this indicator then a seperate purchase requisition is created for every externally processed operation or non-stock component.
Regards,
sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
It would be great if you could provide some more information about your requirement.
In case you are interested in knowing how the collective PR functionality works, please refer SAP Help.
Regards,
Gokul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Gokul,
I have one project in that one 1st level WBSE and three 2nd level WBSEs.
2nd level WBSEs having a Networks, Activities and components. After release a project PR created but each network having a different requisition number.
Client want to make one PR and PO at project level.
So i am trying for the Collective PR indicator but i am not able to do the same.
Thanks.