Question about Planner and CSA

Former Member
0 Kudos

In our PC 3.0 system, I found that the system allows to plan a second CSA for a control for the same time frame if the first CSA is closed.

Is this an error? If  it's not, can someone tell me the logic behind this?

I think the planner should not pick this control as CSA is already performed.

Accepted Solutions (1)

Accepted Solutions (1)

former_member205878
Contributor
0 Kudos

Hi Rakesh,

As per the current functionality of the product, the system will allow you to create a new plan for the

same entity and same timeframe if the previously created plan is closed.

The Business significance of this functionality is if you incase are not satisfied with the assessment or the assessment was not closed properly, there should be a way to repeat assessment for the same timeframe.

Regards,

Silky

Former Member
0 Kudos

Hi Silky,

Thanks you for the reply

Thanks and Regards

Rakesh Sukumar