Hi Experts,
When i am trying to select the costing sheet for wbs in project builder, i am getting below message.
Please help me in this regard.
Thanks & Regards,
Dileep
Check the below post
< Link Deleted>
Thanks
Message was edited by: Moderator - Posting only links as reply is not allowed.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Indirect costs / Overhead costs can be calculated on Material costs based on Percentage / Quantity method.
The process is, if your Client is calculating the OH cost on percentage based / QTY based, then go to
SPRO -> Controlling -> Product Cost Controlling ->Product Cost Planning ->Basic Settings for Material Costing ->Overhead -> Costing Sheet: Components
Here, you have to create a Credit with combination of Cost element (CE category is 41) and assign it with Cost center or Internal order. If the Internal order is a statistical one, you can assign both.
Then Create OH Rate with available options like OH Type and Plant...etc and specify them.
And then, create the Base for OH Calculation. Here, you need to specify the Cost elements group (Material cost elements) which you are taking as base for OH cost.
Then the final step is, define the Costing sheet.
Base Overhead group From To Credit
OKTZ: OH Cost element which you have created for OH Cost with 41 category has to be assigned in Indirect cost in OKTZ. This is mandatory.
And then, assign the cost sheet to the respective Costing variant in OKKN
Also, check the below my post for more details
http://scn.sap.com/thread/3154345
Let us know if you still need any further
Thanks
Hi Narasimhulu,
Thanks for the reply. I have configured the costing sheet alraedy and it is also used in many projects.For some wbs elemets only, i am not able to assign the costing and i am getting the issue.When i analyzed the issue, i found out that for wbs elements in prps table usage & application fields are empty.So it is showing error. I want to know how these fields get updated in prps for wbs.
Thanks,
Dileep
Hi Dileep,
Costing sheet specifies how overhead costs are determined.
You are trying to enter Costing sheet # A40C00 which is not created in the system. Hence system is giving error as mentioned above.
Please go to following path in configuration for creation of costing sheet
SPRO -> Costs-> Automatic and Periodic Allocations -> Overhead -> Costing Sheets -> Define Costing sheet
Once you create new costing sheet , you can try entering costing sheet again in the project builder.
Go through sap help to know more on costing sheet.
http://help.sap.com/saphelp_46c/helpdata/EN/b1/c04880439a11d189410000e829fbbd/frameset.htm
Regards
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
14 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.