Eror when processing AUC for WBS

Former Member
0 Kudos

Hi Experts,

                 I'm working on capex proj scenarios. IM-PS integration.when I release my WBS system should create AUC automatically in DEV i tested and its working fine there.Now, in QAS while releasing WBS I am getting error as "Eror when processing AUC for WBS" & "Enter asset number which is between XXXXX & XXXXX"

Now, when i manually go to create AUC (Edit> WBS> Investm. Programs>AUC) then after entering asset number system is creating auc

however, in DEV just by releasing WBS system is creating AUC.

Is it the correct behavior ?

Kindly suggest.

Thanks & Regards

Manas

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Certainly behavior is not correct.

Check if number ranges is assigned to AuC in your QA system. Take FI-AM consultant's help to dig down in this issue.

Regards,

Mahendra

Former Member
0 Kudos

I think number ranges are assigned. Because system is saying "Enter asset number which is between 951400000 & 951499999" . And when I go via Edit> WBS> Invst. Progrm> AUC > And, here I enter 951400001 at Asset field > back> system status is REL AUC.

But, in DEV , When I release WBS> system status is REL AUC at one.

What's missing, Kindly suggest.

Regards

Manas

former_member209919
Active Contributor
0 Kudos

Hi Manas,

I think you shoul review your number range

Go to the investment profile and extract the number range you have configured XX

Go to AS08 and enter the company code, check the range for number XX, it souldn't be external. And current number has to be in the range.

Regards,

Sara

narasimhulu_konnipati
Active Contributor
0 Kudos

What Sara is said is correct. You should maintain the number range as Internal rather External. If it is external, then system would expect the number in that given range.

Thanks

Former Member
0 Kudos

Thanks Sara.

Issue is resolved now.

Closing the thread.

Regards

Manas