on 12-19-2012 9:54 AM
Hi
Could you please tell me the difference between the costing BOM and production BOM.
Regards.....Bikash.
Hi Bikash,
Usually production BOM is used for production and also for costing purpose, that means Production BOM can give cost estimate, plan and production order calculation.
Where as through Costing BOM you cannot create plan and production order. With Costing BOM you can calculate the cost estimate for a new product which is not yet manufactured.
Regards
Srinivas Salpala