How to use PPDS in ETO scenario

former_member143179
Participant
0 Kudos

Dear Sir,

We are manufacturing Industrial Machinery as per the Customer Order and have ETO scenario .  The customer order receipt to delivery time is approx 7 months and  all engineering activities like Design/BOM/Material Codes/Routing etc are very much customer order specific .

Our objective for using PPDS :

We need to use PPDS for finite scheduling of  the MRP generated planned/production orders for the semi-finish material  for all the running projects . There are almost 70-80 nos projects running simultaneously and the objective is to have  an optimum finite scheduling across all planned orders so that delay of end product delivery is minimized .

Our existing approach :

We are using PS system and PP system also .  In our existing ERP setup , We are creating universal multilevel BOM  for the Finish Product and attach this FERT  with an activity in the Project under a WBS .  This generate a requirement for the FERT .  We subsequently run MRP using MD51 and this generate numerous planned orders and Purchase requisitions .

We then define an integration model between ERP and APO , and generated planned orders/ Purchase Requisition( PRs ) gets ciffed to APO . We are not defining any PDS .

Our Requirement :

We request the forum members to kindly suggest us the ideal approach to be followed for using PPDS with  ERP  in our business scenario , so that our organization is able to get the full benefit of PPDS along with ERP and our objective also gets delivered in an efficient and reliable way .

With regards

B Mittal

Accepted Solutions (0)

Answers (1)

Answers (1)

frank_horlacher
Employee
Employee
0 Kudos

Hi,

consider using MRP-based DS:

MRP-based Detailed Scheduling

there is also an RDS out.

SAP Advanced Production Scheduling rapid-deployment solution


http://service.sap.com/solutionpackages

http://service.sap.com/rds-aps