Hi,Friends
in any Maintenance order how to capture Actual date of order creation and finished date and similarly Actual date of shut down started and finished dates ?
i am little bit confusion?can you please light up on this issue.
Regards,
Kumar
Greetings Kumar,
The actual order creation date is capture on the Order header (Control tab) as "Created on" AUFK-ERDAT & the time of creation is captured as ERFZEIT
What do you mean by the Order actual finish date?
The basic order finish date will be captured as AFKO-GLTRP; that is entered manually or determined by scheduling parameters.
The date of the Technical Completion will be captured as Refrence Date AFIH-ADDAT (time as ADUHR), if your settings are for the Reference Date to be proposed as current (blank) in SPRO (Functions and Settings for Order Types > Define Proposed Reference Time for Technical Completion), or as AUFK-IDAT2
The actual date and time of starting and finishing the Order are updated from confirmations entered as in IW41, as AFKO-GSTRI and AFKO-GETRI, respectively; the actual finish date is only updated if the Final Confirmation is saved.
Hope this helps.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.