Distribution Receipt (Planned) 31,050 = Total Demand 13,634 + Safety Stock 17,416
NOTE.- Remember the master data Reorder Point is 20,000 but the planning book shows the Reorder Point 37,416 = Reorder Point 20,000 + Safety Stock 17,416
Distr. Receipt 51,050 = Tot Demand 13,634 + SS 17,416 + 20,000 Reorder Point
Hi Arnulfo,
The reorder point is not a demand, it is a trigger level. In PP/DS, when you run planning, if the receipts (including stock) - demand quantity falls below the reorder point then the system will trigger replenishment. The replenishment quantity is based upon your lot-size strategies such as whether or not you have set "replenishment to max. stock level". In your case, safety stock won't play in the system decision. PP/DS only considers the reorder point when planning is run. It won't consider any future shortfalls.
If you look at the PP/DS planning results in a SNP planning book, you will get shortages in the future. They will remain until you run SNP planning where the reorder point macro (REORDER_CALC) comes into play.
Best Regards,
Mike
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mike,
You are telling me that if I execute the PPDS Heuristic SAP_PP_007 the system will not include the Reorder Point in the Distribution Receipt, but if I execute the SNP Heuristic the system will include the Reorder Point
Heuristic PPDS
Distr. Receipt 31,050 = Tot Demand 13,634 + SS 17,416
Heuristic SNP
Distr. Receipt 51,050 = Tot Demand 13,634 + SS 17,416 + Reorder Point 20,000
Is the above statement correct?
The SNP Heuristic includes the Reorder Point because execute the macro REORDER_CALC
Is the above statement correct?
Thanks,
Arnulfo Cordero Pradel
Hi Arnulfo,
Comparing the results of a PP/DS planning run seen in the Product View with what you see in the SNP interactive planning book is problematic. The reorder point calculation in PP/DS ignores safety stock. So when you plan a demand, you will get a purchase req. equal to your reorder point if the reorder point is greater than the demand. It will happen once and in the product view you can see that there will be a shortfall with future demands.
In SNP the safety stock is considered in the REORDER_CALC macro function so the reorder point key figure will show product master reorder point plus safety stock. When you run SNP planning you will get a distribution receipt equal to the KF Reorder point (product master reorder point + safety stock) + demand.
If your business case requires SNP to match PP/DS you could adjust the reorder point macro but you have to be careful.
Comparing PP/DS planning with SNP planning is like comparing apples and oranges.
Best Regards,
Mike
Hi,
if you are using both SNP and PP/DS and safety stock is important in both sides, you should considering making SS relevant in PP/DS (activate in planning version, then use heuristic SAP_PP_018 to create SS liveCache orders relevant for PP/DS). You will see SS as additional demand orders.
However, as Mike said, having SNP and PP/DS "agree" is problematic in general.
thanks,
J.