on 12-12-2012 1:57 AM
Hi Experts,
In SRM7.0, if i click ITEMS tag and trigger CHANGE BADI, i would get IT_ITEM with value.
But if i change the HEADER only, i would get IT_ITEM with null value. The question is
under such circumstances, if i want to update the ITEMS value simultaneously with the
change of the HEADER, how do i get the IT_ITEM of the PO?
I've tried obtaining E_ITEM through BBP_PD_PO_GETDETAIL and obtaining IT_ITEM through IMPORT in CHANGE
BADI. But the fields are not consistent. Any suggestions?
Hello,
In this case you can call FM BBP_PD_PO_GETDETAIL with importing GUID.
And also check do u have ET_ITEM is filled??
Thanks,
Neelima