SAP_PP_002 not respecting Sales Order Dates

Former Member
0 Kudos

Hi Experts,

I am running SAP_PP_002 and I have seen that Heuristic is not considering the requirement Date of Sales Orders for creating the Purchase requisitions

.e.g. if the Requirement Date in Sales Order is of 25th Dec and Transportation time is 2 days then rather than creating Preq on 23rd Dec -- system is creating Preq much earlier e.g. 13th Dec.

The scheduling strategy in Heuristic is Backward with reverse.

Kindly help with possible cause.

Rgds,

GIG SL

Accepted Solutions (0)

Answers (1)

Answers (1)

sourabh_jain66
Active Contributor
0 Kudos

Hi,

Are you maintaining any GR time in the product master in APO or ECC.

Please also send some screenshots of the scenario,

Rgds

sourabh