on 12-09-2012 9:41 AM
Dear All,
My Use is required to when he create Production order in co01 that time system ask to manually to which BOM select ?
Steps:
CO01-> Enter all detail -> enter qty AND Date -> press F6 here by default SAP take first BOM. but we want to this process manually.
i had tried in OPL8. here i had select option 1 but not working. and i also changed in material master in MRP4 select 3.
but not working please suggest me solution. thanks in advance.
Regards,
Rakesh
hi,
check the following things:
has this BOM being assigned to Routing?
does the lot sizes match? lot size in Routing, in production version?
what is the validity date of this BOM?
what kind of BOM have you created and what is that u want to use for Production order?
check and confirm these points.
Thanks,
Regards,
Sandeep Kumar. S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.