Hi Expert,

What the use of QM control key in material master quality data teb.

Sunil

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member184536
Active Contributor
0 Kudos

Dear Sunil

Control key is defined for specific function which we want to carryout at the time of procurement of material.

Manish

former_member186193
Active Contributor
0 Kudos

Hi,

QM Control key: Details for QM specific procurement process at plant level are determined using this control key like if Technical delivery terms,Certificaton type etc.

The control keys in the material master are effective at the plant level. They contain the following control indicators:

  • technical delivery term required
  • quality assurance agreement required
  • vendor release required
  • quality certificate required
  • payment block
  • ignore existing blocks
  • notification type , if the system encounters a block

Regards,

Alok Tiwari

Former Member
0 Kudos

Hi Sunil,

QM Control key  is for Details for QM specific procurement process at plant level are determined using this control key like if Technical delivery terms,Certificaton type etc.

QM control key key determines which conditions are valid for quality management in procurement.

QM Procuremrnt Active: if this set it means that QM in procurement is activated for all plants of a client.

When ever you are using Qm procument key better to keep it as simple as possible. 

IMG>> Quality Management -->QM in Logistic --> QM in Procurement -->Define Control Keys

now here After Defining the Control Key, Go to QM in Procurement Tab

When ever you maintain Quality aggremnt tick & Vendor Relase or Delivery relase then Qulaity Info record cum into picture which are to be maintained at plant level..

Thanks and Regards