Guys,
I have a scenario where I am doing Rfx for a Shopping Cart and finally create a PO in EBP. It is Ex. Classic.
PO is successfully replicated in ECC.
Now I also have SUS for supplier order collaboration which is running independent of EBP.
If I am creating a PO in ECC it is successfully replicated to SUS and I complete the process till invoicing without any hitch.
But when I am receiving the PO in ECC from EBP; this PO is not replicated to SUS although I can see the event for EBP PO is trigerred in SWEL.
Would you be able to throw some pointers in this.
Thanks
Hi,
Did you see any XML with service PurchaseOrderERPRequest_Out_V1 sent to SUS system ?
Please check OSS note -
1676004 - ECC Purchase Order is not updated in the history of the SRM documents for sending SOA messages for PO.
Regards,
raghu