FREEZING DP FORCAST

Former Member
0 Kudos

i have freezed the forecast in sap apo dp and send it to sap ecc pp mrp area  where do we find this freezed effect

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

I HAVE FORECAST-ED FOR A MONTH AND FREEZED THAT VALUES AND I WANT TO SENT IT TO SAP ECC PRODUCTION PLANNING

WHEN IAM SENDING MY FREEZED VALUES  WHAT IS THE IMPACT IN ECC PRODUCTION PLANNING

Former Member
0 Kudos

K,

Sending a demand plan to ECC creates planned independent requirements in ECC.  You can view these in MD63 and related transactions.

Unless you can be more specific about what you mean by 'freezed that values', then I would have to say there is no other effect.

Best Regards,

DB49

Private_Member_738444
Participant
0 Kudos

Hi DB49,

After having gome through your replies, I have a small querry.

I wonder how do we send Demand-Plan from APO-DP to R3-PP,  does one use Integration Model for this or Is there a standard procedure like coying the APO-Keyfigure to R3, if yes, how is it done.

Thanks

Lotus

Former Member
0 Kudos
Former Member
0 Kudos

K,

i have freezed the forecast in sap apo dp

I am a bit confused by the meaning of this statement.  Can you first tell me the exact step(s) you took to 'freeze the forecast'?

Best regards,