cancel
Showing results for 
Search instead for 
Did you mean: 

The PR Release date getting changed during confirmation performed in IW41/IW42

former_member533535
Participant
0 Kudos

Hi Experts,

We have PR created from PM Order where the PR have some release date and these PR's get transfered to SRM as SC.

This SC goes for approval and on complete approval PO is getting generated in SRM and replicated to ECC:

The PM user does a confirmation after a week or so in transaction IW41 or IW42.

This changes the PR line item release date and this change in PR gets retransfered to SRM and the approval gets retriggered.

Our client does not needs this IW41 and IW42 confirmation to update the PR release date and hence we need to know if there is any exit or BADI is available to block this change in PR or block the change flowing to PR from IW41/IW42.

Our technical team could not find the enhancement. It would be of great help if we get the enhancements.

Regards,

B.N.Karthikeyan

Accepted Solutions (0)

Answers (1)

Answers (1)

jason_boggans
Active Contributor
0 Kudos

Dear Poster,

As no response has been provided to the thread in some time I must assume the issue is resolved, if the question is still valid please create a new thread rephrasing the query and providing as much data as possible to promote response from the community.

Best Regards,
SDN SRM Moderation Team