Overhead calculation for Production order

Hi,

We have a scenario for a new plant in our company.

Example:

Overhead calculation loaded to the Production order should be like below:

Electricity, water and office overheads posted to cost elements till 31.12.2012 : say 100000

Quantity produced last year: 10,000

If we are producing 100 kgs in a production order, when KGI2 is run the system should calculate for that production order like below:

(1,00,000 OMR/10,000 KGS)*100 kgs which is qty of prod order.

the same way for another production order but the amount would change (100000 may become 102000) but the qty produced last year will be same.

Where we need to give this calculation apart from cost sheet configuration

currently we have defined percentage overhead rates but no wher i am not able to give this calculation.

becouse of this when i run KGI2 for production order the overhead calculation value is zero even though we have given base.

Pl help