Hi,

My project landscape in decoupled scnario. For stiocked items classic Po will create. Remaining products extendclassic scnario will create.

But  I noticed that i have selected stock item from the catalogue and selected the contract. But PR is creating instead of PO. Please advise me what would be the problem.

Thanks in Advance,

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Can you please check note 1173815?

Regards,

Nikhil

laurent_burtaire
Active Contributor
0 Kudos

Hello,

check wiki below:

Follow-on document determination (PR, PO,RS)

Regards.

Laurent.