on 12-03-2012 9:13 AM
what are the necessary configuration (PS configuration and SD configuration) to link procurable materials to a project or network? we were able to create a project from a material in a sales order. however we want to link procurable materials from the sales order to a project.
thanks for your responses.
However we still cannot copy procurable items from sales order to the items components of a project.
can you help us with the settings to link procurable sales order items to material components of a network?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Daniel,
For Assembly processing the following are the steps we need to follow.
Master Data required
1. Create a Standard WBS
2. Create a Standard Network
3. Finished Product that is required to manufacture through assembly process.
4. in T.code CN08 define the relation between Materail/Std WBS/Std Network/Network Type/Network Profile
Settings required In SD Module
1. Define Requirement class with Network type as PS01 or PS04 and with account assignment cat as Q project make to order iif you want all operational as well as materials cost to be accounted at project level with assembly option as 2.
2. define the requirement type and assign the requirement class to requirement typw.
Note: standard settings available in SAP or we can define by our own also.
3. Create a seperate sales document type if required.
Settings in PS
1. In PS if you want all the opeartional cost also to be accounted for at project level from planning onwards then set in t.code OPSV "order level updating" ensure check box for 10 and 20.
Settings in PP
I. Create BOm in T>code CS01
2. Creating Routing for the production operations
Note: For routing we need workcenter and activity types defined already. Cost for activity type in KP26. Not these activity costs related costelements should be part of product costing for cost to flow in all reports as to know the cost of finished product.
Settings in MM
In material master in MRP view we need to set the MRP Group and strategy group relevant for assembly process. As Strategy will have requirement type. (Strategy 85)
proceed with business process after config
also refer http://wiki.sdn.sap.com/wiki/display/PLM/Assembly+Process+in+Project+Systems
thanks
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Daniel,
Apart from links shared by Tushar, you can also search the forum. You'll find lot many threads on the same topic. Search with term "Assembly processing".
Regards,
Amaresh Makal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Daniel,
Assign material that you are using in Sales order to Standard Network of the project in CN08.
Also please refer Settings for Assembly processing in help sap at below mentioned link
http://help.sap.com/saphelp_46c/helpdata/en/95/1613a8837b11d2b6700000e82d8bd1/frameset.htm
In addition below wki threads on Assembly processing can help you
http://wiki.sdn.sap.com/wiki/display/PLM/Assembly+Process+in+Project+Systems
http://wiki.sdn.sap.com/wiki/display/PLM/Assembly+Processing+with+SAP+PS
Regards
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.