PS-SD Integration

Former Member
0 Kudos

what are the necessary configuration (PS configuration and SD configuration) to link procurable materials to a project or network? we were able to create a project from a material in a sales order. however we want to link procurable materials from the sales order to a project.

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

thanks for your responses.

However we still cannot copy procurable items from sales order to the items components of a project.

can you help us with the settings to link procurable sales order items to material components of a network?

sunil_yadav2
Active Contributor
0 Kudos

Dear Dainiel,

We have to transfer all the materials to network activity using CN33.

we dont have any automatic process to copy material from sales order to project. we have to assign BOM header and than transfer BOM component.

thanks

Sunil

sunil_yadav2
Active Contributor
0 Kudos

Hi Daniel,

For Assembly processing the following are the steps we need to follow.

Master Data required

1. Create a Standard WBS

2. Create a Standard Network

3. Finished Product that is required to manufacture through assembly process.

4. in T.code CN08 define the relation between Materail/Std WBS/Std Network/Network Type/Network Profile

Settings required In SD Module

1. Define Requirement class with Network type as PS01 or PS04 and with account assignment cat as Q project make to order iif you want all operational as well as materials cost to be accounted at project level with assembly option as 2.

2. define the requirement type and assign the requirement class to requirement typw.

Note: standard settings available in SAP or we can define by our own also.

3. Create a seperate sales document type if required.

Settings in PS

1. In PS if you want all the opeartional cost also to be accounted for at project level from planning onwards then set in t.code OPSV "order level updating" ensure check box for 10 and 20.

Settings in PP

I. Create BOm in T>code CS01

2. Creating Routing for the production operations

Note: For routing we need workcenter and activity types defined already. Cost for activity type in KP26. Not these activity costs related costelements should be part of product costing for cost to flow in all reports as to know the cost of finished product.

Settings in MM

In material master in MRP view we need to set the MRP Group and strategy group relevant for assembly process. As Strategy will have requirement type. (Strategy 85)

proceed with business process after config

also refer http://wiki.sdn.sap.com/wiki/display/PLM/Assembly+Process+in+Project+Systems

thanks

Sunil

Makal
Active Contributor
0 Kudos

Hi Daniel,

Apart from links shared by Tushar, you can also search the forum. You'll find lot many threads on the same topic. Search with term "Assembly processing".

Regards,

Amaresh Makal

Former Member
0 Kudos

Hello Daniel,

Assign material that you are using in Sales order to Standard Network of the project in CN08.

Also please refer Settings for Assembly processing in help sap at below mentioned link

http://help.sap.com/saphelp_46c/helpdata/en/95/1613a8837b11d2b6700000e82d8bd1/frameset.htm

In addition below wki threads on Assembly processing can help you

http://wiki.sdn.sap.com/wiki/display/PLM/Assembly+Process+in+Project+Systems

http://wiki.sdn.sap.com/wiki/display/PLM/Assembly+Processing+with+SAP+PS

Regards

Tushar