on 11-28-2012 4:45 AM
I have check report S_ALR_87013558 and found available negative. Please kindly help to suggest how this happen?
I distributed buget in CJ30 from IVM> WBS Level 1> WBS Level 3 and total up.
I using buget profile with object currency and buget control overall.
WBS Status are REL BUDG ISBD AVAC NTUP SETC Now and we have daily job run for CJEN and CJBN.
But now view report 13558 and found assigned value more than budget!!! how this happen and how to check it.
Please kindly suggest
Regards,
Ommy
Hi Ommy,
In S_ALR_87013558, as you must be knowing, is the summation of all the cost incurred. These cost are incurred on cost element and consequently is displayed in the report. But some cost element have negative values, such as Revenue cost elements. If these values exceeds much higher than the positive values, the assigned value will be shown negative in the report. Please check in CJI3, whether the summation is negative or not.
Regards,
Manan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please check in Budget profile may be AVAC is just activated for few perticular things.
I have seen same issue once, so thought of sharing it with you.
Hope it will work..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Scenario:Budget Exceed But No Error Message And Availability Negative Now:
Reasons For Error.
1. AVAC functionality Might not be Activated for Inetial postings.
2. Improper Tolerance Limits config.
3.UN even distribution of Budget from Top WBS level to Child Level WBS.
Eg: 3 Scenario: Un Even DISTRIBUTION of Budget :
A: Top WBS: 1000,
A.1, A.2, A.3 are child WBS.
Inetially we didnt distribute the budget amount to child WBS, But try to post some actual postings to Child WBS: A.3, EG:( RS: 200) Then system will allow u to post the transaction, Even though budget is not there in Child WBS, Since it will consume budget from top WBS.( 1000-200 ) =800 Top WBS.
But afterwards distribute the budget to child WBS, 200,
In this system will show available 200 Rs in Child WBS, but actually consumed 200 fom top WBS.
Try to post 150 Rs, in child WBS, since it is showing 200, but system will give Budget Error Message of 200+ 150= 350 ).
Regards,
Kumar.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I suggest you to run CJI3 and do the detailed analysis of all the costs that are accumulating on your project.
Regards,
Amaresh Makal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I have checked tolerance limit, OPSV and exempted cost element. All setting work fine.
tolerance limit,> 80 warning, 100 error
OPSV > checked box for network
and Exempt CE > not use in this WBS.
Please kindly suggest
Regards,
Ommy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI Ommy,
ASsigned value can be greater than budget for different reasons. The most frequent is for the PR/PO flow.
Example : budget = 10000 $.
Material PR commit the cost( 2 UN -- 10.000$) when you create the PO for this PR and the price of the material is greater than the PR ( example 2 UN - 11.000$) the system doesn't check the budget here because it was checked during the PR. Then your assigned value will be 11.000
THe same happens when the price difference is in the GR or in the invoice.
I hope this can be useful,
REgatds
Hi Ommy,
maintain correct tolerance limit and maintain OPSV for appending and assign fund in planning.
thanks
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ommy,
There could be situations that without using exempted cost elements some cost elements may skip the budget check and yet contribute towards the assigned values. One example could be that while creating PRs/POs for project stock(Account Assignment Category Q) the inventory G/L may not be having a corresponding cost element with category 90.Please check on these lines too.
Thanks and Regards
I hope you have configured tolerance limit with correct budget profile.
Regards,
Amaresh Makal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
ISBD is represent insufficient budget so you need to increase budget for concern wbs.
for negative in Available column due to sap standard feature this is equal to (Assigned value = Actual+Commitment+RemOrdPln)
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
92 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.