Billing scenario in Project Manufacturing

former_member143179
Participant
0 Kudos

Dear Sir,

We have a Project Manufacturing scenario , as we are in manufacturing of customized Industrial machine manufacturing . We are looking to know about the steps to be followed as per SAP best practices for the following business scenario .

Business Scenario

We have muti stages complex payment terms fixed with customer for execution of the order . A typical payment terms may be : 10% advance after signing of customer order , 15% advance against the Design approval, 10% advance on submission of Material procurement proof , 50% after 30 days of  dispatch of ordered machine , 15% after 30 days from the successful comissioning of the machine .

For these milestone based payment , concerned department (contract dept) intimate to accounts dept about the relevanr milestone completion  and then for advance claiming , a proforma invoice is raised to customer . Subsequently on receipt of advance payment , it is treated as tarde customer advance . After dispatch of goods ,  advances are adajusted against the Invoices . For last payment (linked with commissioning ) again a proforma invoice is raised .

We want to use SAP for this complete scenario , so that triggering of milestone completion and it's notification , raising of proforma invoice , tracking related to pending proforma invoices , advance adjustment , payment due information and it's pending traking (eg payment to be received against the Bill after 30days from date of supply) etc  can be made available from SAP .  Senior management , should also be able to monitor all pending receiveable in a very clear and easy way .

We request SAP experts to kindly guide us about the steps to be followed to address the above issue please .

With regards

B Mittal

Accepted Solutions (0)

Answers (2)

Answers (2)

jpfriends079
Active Contributor
0 Kudos

This can be handled in SAP in 2 ways:

  • One through Sales Project in SAP Project System. This is beneficial, if your project is long term one & spread over more than one fiscal year.
  • Other one is purely through SAP Sales Distribution. Where Billing plan, that to be milestone one, can take care of your business process.

Regards, JP

siva_vasireddy2
Active Contributor
0 Kudos

hi mittal,

          you need to go with  MTO process which includes costing,Milestone billing ,Multilevel BOM.

yuo can serach for the step by step MTO process in the Google aacordingly you can implement taking support from other module consultants.

Siva vasireddy