GR Processing time , Dependent lot size

former_member182449
Participant
0 Kudos

Dear Sir,

Can I do Scheduling for GR Processing time , Dependent lot size

For Example : 4 Hours Required to Inspect 100 PC and 8 Hours to Inspect 200 PC , time is not fixed and dependent lot size

Can I do that ?? , and what's the setting required to do that in APO and ECC?

Appreciate your Help

BR,

Rami

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member189901
Contributor
0 Kudos

Hii Rami,

GR time we maintined is time time needed to recipt the goods for a perticular order not for quantity.

If your concern is for quantity wise, you can do onething, maintian max lot size for 100 pcs. and put check mark for recipts generated should be individual recipts in material master

So everytime it'll cretae create an order maximum of 100 quanity. and as per your master data it'll take 4 days only..

Regards

Debashis

former_member182449
Participant
0 Kudos

Hi ,

What do mean by GR for particular order not for quantity ??

This time used for scheduling in APO by Handling Resource in Location master

BR ,

Rami