Hai,
Heuristics considers, Quota arrangements, priorities, costs, source validity and lot sizing in sequence as factors. Can I customize the order lets say, I want to consider myHeuristics Priorities, quota arrangements, due dates, costs and lot sizes. Can I do this? If obseved properly, in my question above, due dates(not part of actual sequence)is also included. Is there any scope of customizing? How? with what?
Thank you.
Hi Vishu ,
This is very good question you have asked ..
yes you can modify the sequence
You can use the BAdI /SAPAPO/PWB_SOS to modify the content and the sequence of the sources of supply in the ranking list. For example, you can sort the sources of supply according to procurement costs and then according to procurement priority.
also go through <a href="http://help.sap.com/saphelp_scm40/helpdata/en/bc/36ac3a22f0785ce10000000a11402f/frameset.htm">Source Determination (Heuristic)</a>
Redgs //Digs...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
what u refer to is called the supply ranking list for SNP heuristics
there is some more detail on the the default sequence <a href="http://help.sap.com/saphelp_scm40/helpdata/en/47/37934e7ff19d4cb3b7084291a8259a/content.htm">here</a>and also talks about the BADi /SAPAPO/PWB_SOS for changing the sequence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
6 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.