on 11-23-2012 12:33 PM
Hi Experts
We want to upgrade our SAP_APPL from 13 to 18.
I have found out the dependent patches from SMP.
Our current SP level is:
SAP_ABA 700 0015
SAP_BASIS 700 0015
PI_BASIS 2006_1_700 0005
ST-PI 2008_1_700 0001
SAP_BW 700 0017
SAP_AP 700 0013
SAP_APPL 600 0013
For upgrading APPL to 18, we have to upgrade BW to 24, BASIS and ABAP to 22, AP to 21 and PI to 12.
Following are the patches I need to apply, also in the following order.
1 | SAPKB70016 |
2 | SAPKA70016 |
3 | SAPKB70017 |
4 | SAPKA70017 |
5 | SAPKB70018 |
6 | SAPKA70018 |
7 | SAPKB70019 |
8 | SAPKA70019 |
9 | SAPKB70020 |
10 | SAPKA70020 |
11 | SAPKB70021 |
12 | SAPKA70021 |
13 | SAPKA70022 |
14 | SAPKA70022 |
15 | SAPKIPYM06 |
16 | SAPKIPYM07 |
17 | SAPKIPYM08 |
18 | SAPKIPYM09 |
19 | SAPKIPYM10 |
20 | SAPKIPYM11 |
21 | SAPKIPYM12 |
22 | SAPKW70018 |
23 | SAPKW70019 |
24 | SAPKW70020 |
25 | SAPKW70021 |
26 | SAPKW70022 |
27 | SAPKW70023 |
28 | SAPKW70024 |
29 | SAPKNA7014 |
30 | SAPKNA7015 |
31 | SAPKNA7016 |
32 | SAPKNA7017 |
33 | SAPKNA7018 |
34 | SAPKNA7019 |
35 | SAPKNA7020 |
36 | SAPKNA7021 |
37 | SAPKH60014 |
38 | SAPKH60015 |
39 | SAPKH60016 |
40 | SAPKH60017 |
41 | SAPKH60018 |
I am getting very worried about applying the above patches.
I am not sure about other dependencies also, other than that of software components.
Can you please help me out, and suggest me the pre requisites on the same.
Also, on how should I make the Queue for the patches
Thanks
Harikrishna
Hi Hari,
First you take backup of your system and generate the stack xml from from solution manager it will calculate all the dependencies and after tht apply all these patch by using SUM.
THks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Harikrishna,
I would definitely recommend to implemnet a support package stack as opposed to a collection of individual support packages.
Support package stacks
http://service.sap.com/sp-stacks
are a collection of support packages tested and documented together.
In the same location, you will find documentation on any side effects of applying the SP stacks and you can be assured that they have been thoroughly tested and applied by many customers.
To address dependencies, you should down support package stacks using solution manager maintenance optimizer as this will asjk you what target stack you want to go for. Then it will check your current sp levels and pull in any required support packages to ensure all depencies are met. This will remove manual effort and any risk of error when apply the sp package stack.
Regards,
Paul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Harikrishna,
You have to meet the prerequisite of the packages. So it is not possible to apply the FINBASIS
packages without meeting the prerequisite.
You can define one queue with the FINBASIS & other prerequisite packages. If you have issue in
defining the queue, please let me know and I shall help you to define the queue.
Regards,
Gaurav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
10 | |
10 | |
10 | |
7 | |
6 | |
6 | |
5 | |
4 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.