cancel
Showing results for 
Search instead for 
Did you mean: 

Automatic lot generation for storage condition in stability study

former_member184536
Active Contributor
0 Kudos

Hi Guys

I am doing stabilty study but when i shceduled the the maintenance plan, it shows the planed dates and scheduled date in schedule overviewlist but automatic lot are not created for storage conditions.

Can anyone tell me what i am missing for automatic lot geneation.

Manual lot are created for storage conditions with the help of activitited in action box. But my requirment is that lot must be generated for test dates as per the scheduled.

Manish

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member207800
Active Contributor
0 Kudos

Define background job for ABAP program RISTRA20 with variant.

When date reach scheduled date, SAP will generate insp. lot.

Please check IP30 more detail in EAM forum.

Regards, DoWook KIM

Former Member
0 Kudos

Hi

for this you need to schedule the plan either in IP30 or in SM35.

Here you define the background job to run the schedule with a frequency may be daily or as per your requirement.

Thanks

Sachin

former_member184536
Active Contributor
0 Kudos

Hi Sachin

Thanks for your reply.

But i have already shceduled it in ip30 but lots are genereated automaitcally, it is showing planned dated and call dated as per the shcedule.

Is any config i have missed out?

Manish