Dear All,

Whenever Project material's quantity is changed, i am maintaining a Project Version for that.

But in Standard report CN41, S_ALR_87013538, material quantity and it's value doesn't replicated.

Please reply.

Thanks.

Message was edited by: Mohamed Rafi I have edited the Title for you this time, next time onwards follow the rules.

Accepted Solutions (0)

Answers (3)

Answers (3)

0 Kudos

Solved.

former_member203108
Active Contributor
0 Kudos

Close the thread properly

Makal
Active Contributor
0 Kudos

Read Rules of Engagement.

Most of the guys here respond, whether you highlight it urgent or not. So do not create threads with such titles going forward.

Regards,

Amaresh Makal

0 Kudos

Dear Amaresh,

Sorry for the status of the threads, I am new in this Discussion forum so i don't know the basic rules. Thanks for the indicated me.

Former Member
0 Kudos

Hi,

Project version can be manually created while changing the WBS, network, in the Structure/Dates information system for one or more projects.

You can use the transaction CN71, CN72.

For CN41, please do as mentioned below and check.

1. In menu goto  EDIT--> Scope of Current data --> All Fields

    Subsequently you will get one popup where you can click on YES.

2. Then in main menu goto Evaluation --> Save Project Version

3. Use specific nomenclature for Version key & Version group and execute.

    It will save with specific Project version name that you gave.

Try this in test system and verify.

Regards

Tushar