on 11-21-2012 11:59 AM
Dear Gurus,
I have to configure Charms for R3(ehp6 ecc6) and BI landscapes.But currently we have only 1 R3 system(SID--ED1) which is on rental hardware.Real development system(ECD) will be built by system copy of ED1.
1.Can i configure charms with virtual systems in ED1.
2.If possible then what are post system copy activities I have to do on real developmen system.
If not possible please suggest a sutiable solution for the above scenario.
I have gone through https://websmp109.sap-ag.de/rkt-solman and http://scn.sap.com/people/dolores.correa/blog/2008/07/26/first-steps-to-work-with-change-request-man...
Thanks,
Amarnath
Hi
check Q4 here for virtual systems and it will answer ur queries
Regards
Prakhar Saxena
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Gurus,
Now i have two real systems(DEV,QAS) and one virtual system(PRD).
Facing issue while Activate Change management error show below
no consolidation system found for sid-100
No track for project <poroject> with log. system sid/client
Message from function module /TMWFLOW/CHECK_PRJ_CONS: No export system for SID-client.
I have done below things.
1. STMS configured with standard three system route and created domain link between solman and R3 domain controller also pre TMS steps performed(tp parmater CTC=1) etc.
2. Created systems in SMSY with required RFC and assigned the landscape to respective logical components.
3. Created project,added these logical component in SYSTEMS TAB(SYSTEM LANDSCAPE) and created IMG Project(IMG TAB).
But when activate Change request management resulting above.
I searched sdn fourum for the same found a solution that I need to create single route in the entire landscape.
But which layer i need configure (i.eSAP and Z<SID>) between DEV to QAS and QAS to PRD.I here by attached the configured transport route in STMS
Kindly guide me ASAP. I need your help urgently.
Thanks,
Amarnath
hi,
consolidation route is nothing but the route starts from your dev system, its normally dev -> qa, after looking at your screen shot, no issue in the route. But the issue might be with the client. because Charm is client specific.
have you added the appropriate client in stms under your consolidation route.
if you not known the steps, please follow step 2 on the below guide
Thanks
Jansi