Project Status report in cprojects

Former Member
0 Kudos

Hi All,

Please let me know what all the standard reports available in cProjects apart from project status report.

can we get any graphical reports like pie-charts, histograms, bar-charts & etc related to project details.

Regards,

arun

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Ruhnjun/Pramod,

thanks for the reply.

Off lately I found that cProjects analytics add-on can help in getting the reports which I am looking for. But till now i couldn't get the right person from SAP, who could give me any information on this billable solution.

anyways thanks for your responses.

Regards,

Arun

Former Member
0 Kudos

Hi Arun,

In addition to what Runjhun mentioned above, specific to have pie-charts, histograms or bar charts, you need to activate BCV content in PPM 5.0. cProjects provides you side panel reporting in project structure as well for resources.

Please let us know if you have any specific query otherwise you can SAP PPM config guide to get more information about BCV reporting in PPM.

Regards,

Pramod

Former Member
0 Kudos

Hi Arun,

You can use Evaluation engine functionality in cProjects to evaluate operational project for real time data. Many reports can be generated for analysing costing and project schedule. Evaluations can be created for project roles and task assignments.

You can also define your own rules for any specific requirement under IMG node cProjects > Evaluations.

Let me know if it helps.

Thanks,

Runjhun