Collective PR in Assembly processing

former_member299514
Participant
0 Kudos

In our project three different networks are generated from three materials in Sales Order. In all these 3 network header there are individual network activity with one material assigned to each activity. These 3 materials assigned to different networks are creating 3 different PR.

Our requirement is it should generate only one PR with all the 3 line items. I have checked Network Type parameters and here collective requisition is ticked.

Anybody can suggest?

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member203108
Active Contributor
0 Kudos

Meaning of collective requisiton is generation of one PR for a single network, doesnt mean that it will generate one PR for project.

I would suggest two option

1. Requirement grouping

2. Collective PR indicator in project definition ( EHP3)

Former Member
0 Kudos

I think collective PR is going to generate only for non-stock component or services from a single network.

It will be better if you use MRP generated PR and also use 'requirement grouping'.

Regards,

Mahendra

former_member299514
Participant
0 Kudos

Hi mahendra we dont have MRP here.