on 11-20-2012 7:17 AM
In our project three different networks are generated from three materials in Sales Order. In all these 3 network header there are individual network activity with one material assigned to each activity. These 3 materials assigned to different networks are creating 3 different PR.
Our requirement is it should generate only one PR with all the 3 line items. I have checked Network Type parameters and here collective requisition is ticked.
Anybody can suggest?
Meaning of collective requisiton is generation of one PR for a single network, doesnt mean that it will generate one PR for project.
I would suggest two option
1. Requirement grouping
2. Collective PR indicator in project definition ( EHP3)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I think collective PR is going to generate only for non-stock component or services from a single network.
It will be better if you use MRP generated PR and also use 'requirement grouping'.
Regards,
Mahendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.