Difference in MD04 and SAPAPO/RRP3

ryan_lazaro3
Participant
0 Kudos

Hi Guru,

May i ask your help to get inputs and idea on how to check why there is a difference on Available requirement Date between ECC MD04 and APO SAPAPO/RRP3 on our system. Please help where we can check the cause for this.

Sample:

MD04 - MATABC

Req Date      Prod Ord  Qty Peg Req   Lastest Req  MRP Ele

16.11.2012911111121111126.11.2012OrdRes
21.11.2012911112121111222.11.2012OrdRes
21.11.201280000001211112DepReq
22.11.2012911113121111223.11.2012OrdRes
22.11.2012911114121111322.11.2012OrdRes
23.11.2012911115121111103.12.2012OrdRes
23.11.2012911116121111103.12.2012OrdRes
23.11.2012911117121111226.11.2012OrdRes
23.11.2012911118121111226.11.2012OrdRes
27.11.201281111111211112DepReq
29.11.2012911119121111230.11.2012OrdRes
29.11.2012911120121111230.11.2012OrdRes

SAPAPO/RRP3 - MATABC

Req Date    Req Elem   Qty  Category

24.11.20129111111OrdRes (W)
21.11.20129111121OrdRes (W)
21.11.201280000001DepDmd
24.11.20129111131OrdRes (W)
22.11.20129111141OrdRes (W)
01.12.20129111151OrdRes
01.12.20129111161OrdRes
25.11.20129111171OrdRes
25.11.20129111181OrdRes
27.11.201281111111DepDmd
01.12.20129111191OrdRes
01.12.20129111201OrdRes

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member189901
Contributor
0 Kudos

Hii Ryan,

Did you run CCR report for the same ? Check in diffrence in content in that report,....

if you found in diffrence in content then move them to coreesponding system ( APO or ECC )

/sapapo/ccr/...

Regards

Debashis

wilian_segatto
Employee
Employee
0 Kudos

Hi!

/MD04 displays Basic Start/Finish Dates.

/SAPAPO/RRP3 displays always the Availability Dates (Scheduled dates in ECC).

This seems to be correct. But check the Delta Report as well just to be sure.

Best regards,

Will

ryan_lazaro3
Participant
0 Kudos

Hi Guru,

I have checked APO CCR, and find out no item to be reconcile to my product. Still not in sychn.. Please help.

In ECC MD04 example of difference.

23.11.2012   OrdRes   100705   (inside it is a production order 300300)

inside PRDORD 300300

Basic Dates

Start Date : 22.11.2012

End Date : 04.12.2012

Schedule Dates

Start Date : 22.11.2012

End Date : 03.12.2012

In APO RRP3 example of difference.

01.12.2012  OrdRes (W)  300300

Hope this example can help you check our issue

wilian_segatto
Employee
Employee
0 Kudos

Perhaps you have maintained a GI time in ECC?

ryan_lazaro3
Participant
0 Kudos

Hi,

Thanks for the response. May you guide me where i can check the GI time in ECC for my material? And how it affect in the computation? Any formula to compute it? Thanks