Hi Gurus,

I created end to end scenario both in ESR and ID.

I tested from end to end and working fine.

Later as per the business i cahnged mapping and activated again.

It is also working fine as per the business.

Now its the time to move to the QA. So I exported all ESR objects and ID objects.

Now its the time to release them in ESR, here I have two version for Mapping in the chage list.

Which vesrion I have to release and what is the concept behind this versions?

Regards,

Sreeni.

Accepted Solutions (1)

Accepted Solutions (1)

naveen_chichili
Active Contributor
0 Kudos

Hi Sreeni,

You need to open the mapping in QA and display the imported version and select the displayed version in the top right corner and then activate your mapping.

then your mapping will work as expected and last changes will be displayed.

what is the concept behind this versions?

>>>if you go to QA and edit the mapping directly and again if you try to transport the same mapping from DEV in this case you will get this problem.As per the SAP recommendation you should not edit the IR/ESR objects in QA Server...

Always do the changes in DEV and then transport them to QA.

CHeers....!!

Naveen.