on 11-13-2012 10:27 PM
Hi All,
Got user requirement to create two new DMR's in Production system and update more than 5K materials
Currently these materials are not having DMR in Quality Plan, and there is only one common Q plan shared by all these materials
Need to complete this activity in Production client, can you please guide me the steps i should be following to complete this activity?
DMR will be at lot level and is succesfully tested in Q environment
Thanks
Diwakar
It sounds like you have one plan, and two new DMR rules.
So you'll have to copy the plan using QP01 and using the copy model button specify the old plan to copy from.
Update the DMR as required.
The problem you'll have is all 5000 materials will be assinged to both plans if you copied it correctly. You could delete all material assignments first, before copying, from the plan using program RQPREDE2 and than make the copy so both plans have no assignments.
Then use an LSMW to make the new materials assignments or use CWBQM to manually assign them.
FF
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
DMR assigment is at header level in quality plan, so u need to assign two operation in quality plan and assign both DMR in those operations. When ur production order posted then during RR select the operation with perpefct DMR rule and process the UD and RR. and as far as material assigment is concer first check how many falls in 1st DMR rule category and assign all those material in 1st operation and check remaining and assign with 2nd operation with 2nd DMR rule.
Regards
There is no way to update the historical data. It basically starts at zero again. You can manually put it at a specific stage and once you do an analysis of your current records you could group those that are on similar stages together and probably update them via an LSMW and put the vendor at the right stage of the DMR. But you won't be able to specify for instance that they have two approved lots. Or one failed, etc...
FF
Hi FF,
Yes thats the way, i think using QDL2 , I can upload next historical stage for vendor material and plant combination once i assign DMR in Q plan, so the next receipt will take that stage
Whatever current manul tracking stage will remain on paper for record, and thereon everything will be in SAP, sounds ok
Now to summerise it,
1) Create 2 DMR's in PRD system
2) Create 2 Q plans in Production system and assign seperate DMR's in header at lot level
3) Delete material assignment from exisiting Q plan for these materials and reassign to new Q plans
4) Update QDL2 using LSMW
Is that ok plan?
Well. the devil is in the details! Being in a regulated enviorment, (as am I), you need ot err on the side of caution. So I would be cautious about putting any material into a skip lot stage. Lets say you inspect every tenth receipt for a material from vendor. If the you are on the 6th skip lot and you assing the level to a skip level, i believe it will start the count over with the new rule. So you'll now do ten more skip lots, plus the previous 6 for a total of 16 skip lots prior to the next inspection. BUT.. check it out in a dev system. If the DMR criteria is just the material and vendor, you might not have to make any changes. If it is task list, material, vendor criteria, then you'll have problems.
FF
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.