When running MRP at supplying plant MRP is not considering STR as a requirement

Former Member
0 Kudos

Please help me in this.


When running MRP at supplying plant MRP is not considering STR as a requirement.


Scenario:


Receiving plant : STR is generated during MRP run to supplying plant for 100 quanitity


Supplying plant :


Initial stock is 0

Reorder point 100, fixed lot size 100

MD04 shows STR for 100 qty from receiving plant


When MRP is run at supplying plant , PR is getting generated only for 100 qty to satisfy reorder point.


Ideally isn't the qty in PR should be 200 ( 100 for reorder point, 100 for STR requirement)? Do we need to do any customized settings for this? Can any one help me in this.


Regards

Ranjjini

Accepted Solutions (0)

Answers (1)

Answers (1)

0 Kudos

Dear Ranjjini,

Please, address your question to SCN PP Space http://scn.sap.com/community/erp/manufacturing-pp/content

Regards,

Alex.