former_member299514
Participant
0 Kudos

Working on an assembly processing scenario. I did the steps for assembly processing. When I am trying to create a sales order now it is asking for an account assignment to a WBS. So I understand I need to create the project first. The SO will trigger Network and Newtork activity.

My requirement is to also trigger a project from SO. Is this possible?

One more thing, since I have also assigned a material to the standard network why then the material component is not shown in project builder? I have to seperately assign the material to the activity. How can I automate this material assignment?

Accepted Solutions (0)

Answers (3)

Answers (3)

sunil_yadav2
Active Contributor
0 Kudos

Dear Suman,

Please check below links for project creation from sales order or assembly process.

you need to set CN08, CJ91, CN01, etc for this.

http://scn.sap.com/thread/1961208

http://scn.sap.com/thread/1997148

Makal
Active Contributor
0 Kudos

There are lot of threads on this topic in the forum and also couple of good WiKi contents available. You should always search the forum, before posting the question.

Refer following Wiki Links:

http://wiki.sdn.sap.com/wiki/display/PLM/Assembly+Processing+with+SAP+PS

http://wiki.sdn.sap.com/wiki/display/PLM/Assembly+Process+in+Project+Systems

http://scn.sap.com/docs/DOC-33203

Few SDN discussions:

http://scn.sap.com/thread/1416776

http://scn.sap.com/thread/1447130

http://scn.sap.com/thread/2029208

http://scn.sap.com/thread/1325110

http://scn.sap.com/thread/1012238

http://scn.sap.com/thread/1319013

http://scn.sap.com/thread/1049031

http://scn.sap.com/thread/1631024

There are over 200 threads in the forum on this topic. Search & read.

Wiki content, SAP help & forum threads are sufficient to become master in assembly processing.

Regards,

Amaresh Makal

virendra_pal
Active Contributor
0 Kudos

Read SAP help

There are various threads for assembly processing

Various settings are required to achieve this and I suggest aht you go through your set up again

Regards to your specific issue

WBS - account assignment - not required, just save it should assign automatically - make sure that the sales order has the incompletion log set up correctly

material to standard network should be done using Material BOM - if this is done correctly then it works fine - standard functionality in SAP