Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Project creation from sales order

Working on an assembly processing scenario. I did the steps for assembly processing. When I am trying to create a sales order now it is asking for an account assignment to a WBS. So I understand I need to create the project first. The SO will trigger Network and Newtork activity.

My requirement is to also trigger a project from SO. Is this possible?

One more thing, since I have also assigned a material to the standard network why then the material component is not shown in project builder? I have to seperately assign the material to the activity. How can I automate this material assignment?

Not what you were looking for? View more on this topic or Ask a question