on 11-10-2012 11:54 AM
You can run sales pricing in the following ways:
Dp81 is use for sales pricing with Planning in project that has a inquiry number as well.
where as dp82 is use for sales pricing with Easy Cost Planning.
is there any way possible that we do sales pricing using project planning but without mentioning inquiry number in dp81?
Regards.
Hi,
Always search the forum before posting any question. This topic has been discussed many times before.
Refer following
http://scn.sap.com/thread/1373731
http://scn.sap.com/thread/1551488
http://scn.sap.com/thread/1430748
http://scn.sap.com/thread/1028520
http://scn.sap.com/thread/1795882
To answer your question in simple, Yes you can do sales pricing without creating sales inquiry and using any cost planning method. In DIP profile select "Planned cost - Total" in source. Do your cost planning & run sales pricing transaction.
Regards,
Amaresh Makal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.