on 11-10-2012 8:14 AM
My requirement is to configure SPC. now after configuring SPC user wants a monitering report.
Scope-How will the report work?
Well the report should generate a notification indication like certain materials(for exacmple material A's critical parameter (internal diameter measurement) was checked on 10.04.2012. Its next scheduled date is after 6 months i.e 10.10.2012. Please guide me from where to start. Please consider that i will map the SPC somehow, but what is to be done after that.?
Hi
This is part of schduling the work. For this we need batch management so that we can do the schduling accordingly
Batch management option in material management
Next inspection date in batch MSC2N
Inspection interval mentioned in days in quality managment view
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Use tcode QGC3
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.