Hi All, Can we get the report of a project Date-wise?  i.e when ever we run the report  S_ALR_87013558 , it will show the report as on date, suppose we want to see  what the status for project between some dates, how should we check?   Regards, Mandar

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member1009083
Contributor
0 Kudos

Hi,

   For Project wise Actual Cost between some dates you can check CJI3

   For Project wise Commitment between some dates you can check CJI5

   For Budget Line items for Project you can check CJI1 . After executing the report in Chane Layout option you will find the Document date

Regards

Diptadhi


Former Member
0 Kudos

I think all the cost report are available on closing period basis or as on date basis.

You can create report in report painter if you are interested in evaluating report data for a certain period.

Regards,

Mahendra

sanjeevc
Active Contributor
0 Kudos

you can use dynamic selection or shift F4 where you will get lot of date option select one of them according to your requirement and execute concern report.