Extracting Data through RPSCO

Former Member
0 Kudos

Hi Everyone,

I am trying to identify how to extract Rem Ord Pln value from RPSCO. Though I can see Rem Ord Pln values in Hierachical reports the same is not been mentioned in RPSCO table with Value Type 25.

However if I deduct the actuals and commitments (value type 4, 21 and 22) from the plan value (val type 1) for all orders and networks which are taged to WBS elements it get equls to the Rem Ord Pln value.

If this is a viable way to extract the Rem Ord Pln value from RPSCO?

Regards,

Mark   

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member203108
Active Contributor
0 Kudos

Mark,

Refer this note 922177 , SAP has provided a utility program to calculate the ROP values.

Former Member
0 Kudos

Hi Mark,

In my frank opinion this would be the most sensible way of extracting the RemOrdPlan value.

As far as my understanding goes, RemOrdPlan is a calculated value i.e. there is no transaction that actually posts this value directly on any object. As you have mentioned in your post, it is a simple mathematical calculation between actuals and commitments.

I would suggest you to adopt the same methodology and deduce the value for RemOrdPlan.

Regards,

Gokul