on 11-08-2012 3:20 PM
Dear Experts:
I have a requeriment regarding engineering master data, where my engineers need's a report that have multilevel BOM and Routing informations in the same screen / transaction, like transaction CS12, but with routing informations (operations standard values).
In PP module (SAP ECC), not exist a transaction that fits our requirement. We test the transactions CEWB, CU04.
The question is: Have a transaction that fits our requirement in the SAP PLM?
Thanks a lot.
Best Regards,
SOLMAN
Hi,
If standart cost estimate is calculated for the top level materials in consideration, you might use reports CK13N and CK86_99. If not you might have the system calculate the estimate via CK11N.
Regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Andrés:
Thanks a lot for your quickly reply.
We test the transaction CC04 (in the question, i wrote wrong, when i wrote CU04 i mean CC04).
The problem is that the in CC04 i can not run a sum of the standard values, to know the total time to produce entire production levels, in others words, the layout not fits our requirement.
Other sugestion?
Best regards,
SOLMAN