on 11-08-2012 6:26 AM
Dear All,
My client want to change profit center with new defined Profit Center. we can change with mass change but what will be the effect of this change on project or any report.
How we can solve this problem in Existing Projects.
Thanks
Sunil
we have created BAPI for this task
replaced profit center in only open documents where no subsequent document posted.
thanks
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
For your 1st Requirement go to Transaction Code CNMASS, & enter the following:
(a) Database Profile 000000000001[Standard Selection Structure]
(b) Give your Project Definition where you want to change your Profit Center
(c) Then go to Enter field values for mass changes
(d) Click on WBS element, choose Profit Center as your selection criteria
(e) Then in New Value give the New Profit Center & in Replace Only button give the Old Profit Center & Execute it.
(f) In the same way you need to change Profit Center for Network & Activities
For your 2nd Requirement go to Transaction Code 9KE0 & transfer your Profit Center documents from one profit center to another profit center
Regards
Diptadhi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
With regards to Project you have to change Profit Center in the following :
Project Definition
WBS Element
Network
Activity
It will not affect your past data, only all new transactions regarding Project will hit in New Profit Center. Your all Project report will remain the same, only Profit Center Reporting [KE5Z] will be changed
If you are reversing all Old Profit Center related data, then there is no need of any transfer. However if you want to transfer the datas from Old Profit Center to New Profit Center through Transaction Code 9KE0.
After change of Profit Center any project related cost will flow to new Profit Center
Regards
Diptadhi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Experts,
I need your help regarding profit center replacement (New Profit Center in place of old PC in Existing/Open Projects).
According to me, On change of profit centre from Old to New, project accounting report may not available. There can be discrepancy in reporting as complete project profitability may not obtain there.
Here we are going to remove all the existing PO,PR for that project and remove all CATS data also.
After changing Profit center in Master data like Materials, WBS,etc than we can recreate these documents. So all the projects comes in same status.
For Ex: Project 1 having actual cost 100000 and commitment 150000 so we have to make it 0 for both
Change Profit center in project than recreate all the documents.
If I am wrong than Please guide me right process to achieve this.
Please share your experiences.
thanks
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
If you change to New Profit Center from Old Profit Center, it will not affect any project accounting. In CJI3 , There will be no issue regarding Project/WBS wise actual Cost.
However you must note that previous all data posted [KE5Z] in Old Profit Center will not go to New Profit Center. You have to transfer the datas from Old Profit Center to New Profit Center through Transaction Code 9KE0.
After change of Profit Center any project related cost will flow to new Profit Center
Regards
Diptadhi
Hi,
Please check first does it allow you to change the profit center in project. The reason for that is many times we make that field as uneditable.
The impact of change in profit center: No impact on the project however, at profit center reporting level, you need to reference two profit centers instead of one.
1. If you have postings already on old profit center, then let it continue.
2. after changing to new profit center all the new postings would be on new PC instead of old PC.
Now coming to your question, I did not understand that why you want to change PC at material master data etc. Not required and continue as you have now.
3.Why you want to change profit center at material master data. Not at all required. Note that profit center at material master data would always referenced to the plant level. When materials are added to project objects for any kind of postings, the costs will look at PC of WBS and not material master master data PC.
4. Delete the components and corresponding PRs if not converted to POs from project builder.
After changing the PC, then re-assign the material.
If you have already actual costs in previous months, ask your FI team to repost to new profit center from old profit center. As you said in reports you will see total costs split on two profit centers instead of one PC.
Hope this makes sense.
Regards,
Sudhakar
Message was edited by: Sudhakar Pappu
Hi Diptadhi,
Currently we have all type of cost on projects like: Actual/plan/commitment cost via PR, PO GR etc and CATS data on projects, material issue on project from plant, etc.
So now we have to change Old PC to New PC in all masters like material, any relating like workcenter or cost center, Projects etc.
for this purpose we have to reverse all the data from PRD server and assign new PC to all than only we can reassign all data again.
with regard to projects we have to change PC only in WBS, Network and activities.
what else we have to do in respect to Projects.
thanks
Sunil
Hi Sudhakar,
Please check first does it allow you to change the profit center in project. The reason for that is many times we make that field as uneditable.
yes this is editable
The impact of change in profit center: No impact on the project however, at profit center reporting level, you need to reference two profit centers instead of one.
How can we reference two profit centers in reporting.
1. If you have postings already on old profit center, then let it continue.
2. after changing to new profit center all the new postings would be on new PC instead of old PC.
in mid of year when we change PC, than there will be discrepancy in various reports.
Now coming to your question, I did not understand that why you want to change PC at material master data etc. Not required and continue as you have now.
This is business requirement.
3.Why you want to change profit center at material master data. Not at all required. Note that profit center at material master data would always referenced to the plant level. When materials are added to project objects for any kind of postings, the costs will look at PC of WBS and not material master master data PC.
Currently materials are also used without projects also like any PO.
4. Delete the components and corresponding PRs if not converted to POs from project builder.
After changing the PC, then re-assign the material.
thats ok but what about existing PO with 10 materials and GR done for 5
If you have already actual costs in previous months, ask your FI team to repost to new profit center from old profit center. As you said in reports you will see total costs split on two profit centers instead of one PC.
if we do posting to New PC than what if materials having old one and we process same material again after this.
Please suggest.
thanks
Sunil
Hi Sunil,
Please check first does it allow you to change the profit center in project. The reason for that is many times we make that field as uneditable.
yes this is editable
The impact of change in profit center: No impact on the project however, at profit center reporting level, you need to reference two profit centers instead of one.
How can we reference two profit centers in reporting.
1. If you have postings already on old profit center, then let it continue.
2. after changing to new profit center all the new postings would be on new PC instead of old PC.
in mid of year when we change PC, than there will be discrepancy in various reports.
Now coming to your question, I did not understand that why you want to change PC at material master data etc. Not required and continue as you have now.
This is business requirement.
3.Why you want to change profit center at material master data. Not at all required. Note that profit center at material master data would always referenced to the plant level. When materials are added to project objects for any kind of postings, the costs will look at PC of WBS and not material master master data PC.
Currently materials are also used without projects also like any PO.
4. Delete the components and corresponding PRs if not converted to POs from project builder.
After changing the PC, then re-assign the material.
thats ok but what about existing PO with 10 materials and GR done for 5
If you have already actual costs in previous months, ask your FI team to repost to new profit center from old profit center. As you said in reports you will see total costs split on two profit centers instead of one PC.
if we do posting to New PC than what if materials having old one and we process same material again after this.
Regards,
Sudhakar
Hi,
With regards to project you have to change Profit Center in the following :
Project Definition
WBS Element
Network
Activity
It will not affect your past data, only all new transactions regarding Project will hit in New Profit Center. Your all Project report will remain the same, only Profit Center Reporting [KE5Z] will be changed
Regards
Diptadhi
Hi Sudhakar,
with regard to project only what we need to do for replacing old PC to new PC.
it would be great if you provide steps for doing this task.
according to me now what i understand:
Please guide me.
thanks
Sunil
Hi,
according to me now what i understand:
please guide for this. and what about CATS data bcos we have costcenter assigned Profit center also.
it would be great if you provide steps for doing this task.
thanks
Sunil
User | Count |
---|---|
93 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.