we are trying to perform revenue planning in cj42 based on the cost planned in cj40, or in unit costing done in cj40.
But the issue here is in "plan total" coulum in cj42, plan cost is not reflecting at all. per my understanding "plan cost in cj40" should refelct in cj42. but It is not happening now. not knowing the reason why it is not updating.
Please help me with this.
Thanks,
Karthik.
I dont think it will give you planned cost, planned total column in cj42 will display previously planned revenue.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
CJ40 and CJ42 are both independent tcodes for planning costs and revenues respectively. Any change done in any of these tcodes wont affect or reflect in the other one.
I think you have got some incorrect information regarding both these tcodes.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Karthik,
Agree with Mohamed...
Revenue planning can follow same procedure as that is followed in cost planning.
I think, it does not mean plan cost in CJ40 will reflect in CJ42.
Please go through help sap link to know how revenue planning is done
http://help.sap.com/saphelp_erp2004/helpdata/en/4c/22743546e611d189470000e829fbbd/content.htm
Regards
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.