Manual pricing

Former Member
0 Kudos

Dear SD Consultants,

I have configured the DIP to create quotation and billing request from the project and every thing works right ,the steps are as following

1) create quotation using DP81

2) Create sales order with reference to the quotation

3)create billing request using DP91

4)Creating billing

The issue is that in the sales order in addition to the cost there are manual pricing conditions that are used in the sales order but when I create the billing request from DP91 ,the manual pricing conditions are not t copied to the billing request and I can`t figure out why.

I tried all the pricing types in the copy control but none of them works.Can any one help m with thie issue

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member183879
Active Contributor
0 Kudos

Hi,

If you have enabled the billing request for DIP, have you already booked the cost by means of say timesheets and got it approved. If you have enabled DIP through for example say activity types in PS, then, the approved timesheet entries for the activity types will form the basis for the cost in DP91.

I hope you understand the logic. Please let me know if I am missing something.

siva_vasireddy2
Active Contributor
0 Kudos

Hi Farag,

            can you please specify whether it is order relevant billing or Delivery rlevant billing.

Vasireddy